Compare the scope of each line before comparing its headline speed. Map what is included, what is missing and how each machine connects to the next.
- Which conveyors, controls and change parts are included?
- Where does the line lose output during a normal production run?
Keep the line interfaces documented
Before dismantling, label conveyor transfers and record elevations, sensor positions and control links. Retain the agreed equipment list with the photographs. These records help the installation team distinguish supplied connections from interfaces that must be redesigned.
Plan before dismantling
Document layout, cable and pipe routes, reference points, software backups, alignment and the sequence needed for reassembly.
Protect every component
Define cleaning, preservation, labelling, packing, lifting points, transport frames and environmental protection for the journey.
Prepare the destination
Confirm utilities, foundations, access, safety compliance, integration, commissioning resources and acceptance criteria.