Overlay both layouts on the same current floor plan. Keep machine footprint, operator or service space and actual transfer paths separate. Ask what was shortened, bypassed or removed in preparing each adapted layout.
Compare the usable space after installation
| Check | Layout A example | Layout B example |
|---|---|---|
| Clear space at the agreed access point | 1.10 m, short by 0.10 m | 1.35 m, 0.15 m above the specified space |
| Discharge and corner | Turn omitted from the drawing | Turn shown but its supply is still unpriced |
| Service work | Requires redesign or another confirmed route | Verify open panels and removal path on site |
| Decision | Hold until scope corrects the access issue | Compare full price after pricing the missing transfer |
Use the dimensions confirmed by the project team. A positive clearance on one drawing alone does not prove that the complete route fits. Make each omission a named check or line in the quotation.
Use the line interface and relocation guide to identify which original connections a revised plan needs to preserve.