Use the whole shift rather than multiplying steady speed by the scheduled hours. Record accepted units in start-up, stable production and run-out. Keep downtime or change work in the period where it actually occurred.
Calculate accepted output for a short batch
| Phase | Example time | Accepted output |
|---|---|---|
| Preparation and start | 1 hour | 400 |
| Stable production | 6 hours × 5,000 per hour | 30,000 |
| Run-out and release | 1 hour | 300 |
| Whole shift | 8 hours | 30,700, compared with 40,000 if the stable rate were extrapolated |
The illustrative difference is 9,300 bottles. Ask whether the lost shift time or start and end quantities improve on another candidate line. Quote the reliably completed single-shift batch rather than treating every hour as a stable run.